Construction Management Strategy and Performance of Small and Medium-Sized Rural-Road Contractors in Tanga, Tanzania

Authors

DOI:

https://doi.org/10.51137/wrp.ijarbm.931

Keywords:

Construction Management Strategy, SME Contractors, Rural Roads, Procurement Performance

Abstract

Rural roads support socioeconomic development, yet small and medium-sized enterprise (SME) contractors in Tanzania frequently report delays, cost overruns, and quality problems. This study examines associations between four construction management strategy (CMS) dimensions—planning, resource management, monitoring and control, and stakeholder coordination—and construction performance among 245 SME contractors working on projects supervised by the Tanzania Rural and Urban Roads Agency in Tanga Region. A quantitative cross-sectional survey was analysed using descriptive statistics, four supplementary bivariate regressions, and a simultaneous multiple regression. In the combined model, all four dimensions were positively associated with performance: monitoring and control (β = .412, p < .001), resource management (β = .285, p < .001), planning strategy (β = .218, p < .001), and stakeholder coordination (β = .152, p = .011). Together, the four predictors explained 67.4% of observed performance variance (R² = .674; adjusted R² = .669). Because the design is cross-sectional and single-source, these findings indicate association rather than causation. The results identify monitoring and control and resource management as priority capability areas for contractor development, while also supporting integrated improvement across all four dimensions.

Author Biographies

  • Yussuf Masoud, College of Business Education

    College of Business Education, Lecturer

  • Hamisi Sama, College of Business Education

    Department of Procurement and Supplies Management, Senior Lecturer

References

African Development Bank. (2023). African economic outlook 2023: Mobilizing private sector financing for climate and green growth. https://www.afdb.org/en/knowledge/publications/african-economic-outlook

Aloyce, D., Monko, R. J., & Luvara, V. G. M. (2024). Critical audit indicators for assessing construction projects performance (CPP) at pre-contract stage in Tanzania. International Journal of Construction Management, 24(5), 530–539. https://doi.org/10.1080/15623599.2023.2179682

Barney, J. (1991). Firm resources and sustained competitive advantage. Journal of Management, 17(1), 99–120. https://doi.org/10.1177/014920639101700108

Changalima, I. A., & Mwagike, L. R. (2024). The moderating role of staff competency on communication and the effectiveness of force account approach: An empirical study from Tanzania. Cogent Social Sciences, 10(1), 2363600. https://doi.org/10.1080/23311886.2024.2363600

Cohen, J., Cohen, P., West, S. G., & Aiken, L. S. (2003). Applied multiple regression/correlation analysis for the behavioral sciences (3rd ed.). Lawrence Erlbaum Associates.

Creswell, J. W., & Creswell, J. D. (2023). Research design: Qualitative, quantitative, and mixed methods approaches (6th ed.). SAGE.

DeVellis, R. F., & Thorpe, C. T. (2022). Scale development: Theory and applications (5th ed.). SAGE.

Dillman, D. A., Smyth, J. D., & Christian, L. M. (2014). Internet, phone, mail, and mixed-mode surveys: The tailored design method (4th ed.). Wiley.

Makoye, M., Mlinga, R. S., & Ndanshau, M. O. A. (2023). Impact of macroeconomic factors on performance of construction industry in Tanzania. International Journal of Construction Management, 23(15), 2625–2636. https://doi.org/10.1080/15623599.2022.2084259

Podsakoff, P. M., MacKenzie, S. B., Lee, J.-Y., & Podsakoff, N. P. (2003). Common method biases in behavioral research: A critical review of the literature and recommended remedies. Journal of Applied Psychology, 88(5), 879–903. https://doi.org/10.1037/0021-9010.88.5.879

Project Management Institute. (2025). A guide to the project management body of knowledge (PMBOK® guide) (8th ed.).

Public Procurement Regulatory Authority. (2025). Annual performance report on public procurement in Tanzania 2024.

Rehman, M. S. U., Shafiq, M. T., & Ullah, F. (2022). Automated computer vision-based construction progress monitoring: A systematic review. Buildings, 12(7), 1037. https://doi.org/10.3390/buildings12071037

Santos Fonseca, S., Aguilera Benito, P., & Piña Ramírez, C. (2025). Development and application of an innovative planning and monitoring tool to optimize construction projects. Buildings, 15(2), 160. https://doi.org/10.3390/buildings15020160

Tabachnick, B. G., & Fidell, L. S. (2019). Using multivariate statistics (7th ed.). Pearson.

Tanzania Rural and Urban Roads Agency. (2025). Regional performance scorecard: Tanga Region 2024.

Downloads

Published

2026-11-01

Issue

Section

Original Research Paper

How to Cite

Masoud, Y., & Sama, H. (2026). Construction Management Strategy and Performance of Small and Medium-Sized Rural-Road Contractors in Tanga, Tanzania. International Journal of Applied Research in Business and Management, 7(13). https://doi.org/10.51137/wrp.ijarbm.931

Most read articles by the same author(s)